2005 Project
"THE NEW
DRIVEWAY"
Started on Bank Holiday Saturday 28th May 2005
Progress at the
end of the Bank Holiday
Sunday |
10 Tons of
blocks are delivered during the week and carried by hand to the rear of
the house.
This takes two evenings!! |
Relaxing after
the drain has been installed and the soak- away dug
(5th June 2005) |
11th June
2005
Whilst the old tarmac is removed some old crazy paving is uncovered, which has been covered since 1975 |
|
All the tarmac and paving removed by the end of Sunday 12th June |
Early on Monday 20th June the digger moves in !!!
By just after lunch 30 tons of earth has been removed
By the 26th June 13½ tons of crushed rock have been spread and "wackered" down. |
The block laying started on the 3rd July for 3 weekends
The drive finished on
Saturday 23rd July 2005
The finishing touches added on the 31st July (Wings):